Day nursery, Teddington: three-storey steel package
Structural steel supplied, fabricated and erected for a new three-storey day nursery at Udney Park Road, Teddington.
About this project
Steelo supplied, fabricated and erected the structural steel package for a new three-storey day nursery at 2–4 Udney Park Road, Teddington, forming part of a wider redevelopment scheme that also includes three residential properties.
The new nursery has been designed to provide modern childcare facilities across multiple levels, with a substantial structural steel framework supporting the building’s floors, roof and overall configuration.
For this project, Steelo’s preliminary steel package comprised 193 structural beams and 56 steel columns, weighing approximately 49 tonnes. The steelwork incorporated a combination of universal beams (UB), universal columns (UC), parallel flange channels (PFC) and circular hollow sections (CHS), together with specialist connections and selected galvanised columns.
The project required careful coordination of fabrication and installation due to the multi-storey structural arrangement and restricted urban site, with crane-assisted lifting operations and elevated access equipment used during erection.
Steelo undertook both the fabrication and on-site installation, coordinating the delivery and erection of the steelwork to support the wider construction programme.
The completed steel frame provides the primary load-bearing structure for the new nursery, demonstrating Steelo’s capability to deliver substantial structural steel packages for commercial and educational developments, from fabrication through to installation.
On a busy construction site, the biggest challenge isn’t always the weight of the steel — it’s getting every component into exactly the right position.
The new day nursery at Udney Park Road, Teddington, demonstrates the importance of careful planning when erecting a multi-storey steel structure within an established residential neighbourhood.
With approximately 49 tonnes of structural steel identified in the preliminary schedules, the project required coordination between fabrication, delivery and installation, particularly where large beams and columns needed to be lifted into position.
Unlike an open construction site, an urban development presents additional challenges, including restricted access, limited space for lifting equipment and the need to coordinate work safely around neighbouring properties.
The photographs show how mobile crane operations and elevated working platforms were used to position and connect the steelwork at height.
This is where having one contractor responsible for both fabrication and installation makes a real difference. By coordinating these stages, Steelo can plan connection details, delivery sequences and lifting requirements with the practical realities of the site in mind.
The result is a carefully coordinated steel frame that provides the structural foundation for a new space dedicated to early years education.

Project images


Similar work
Commercial steel installation
See how we handle projects like this. Find out more →
More case studies
Browse other projects we have delivered. All case studies →
Send your drawings
Get a price for your own project. Request a quote →
Have a similar project?
Send us your drawings and programme, and we will come back with a quotation.